What You’ll Learn
- Why excavation is an electrical task before it is a digging task: the lines you cannot see are the ones that get hit
- Who must be called before excavation starts, and what the request actually asks for — identifying and marking line locations
- The two-working-days minimum notice, and why calling the morning of the dig fails the procedure
- The six items of information USA DIG needs from the caller, including county, city, street, and nearest intersection
- Why USA DIG is not the whole answer: non-member utilities must be contacted separately, and discovered utilities must be marked and kept briefed to every exposed worker
The Hazard You Cannot See
Overhead lines at least announce themselves. Underground lines give no warning at all, which is why Section N.4.4 of Informative Annex N treats excavation as a locating exercise first and a digging exercise second. The trigger is possibility, not certainty: before excavation starts, wherever there exists a reasonable possibility of contacting electrical or utility lines or equipment, a call is made and a request goes in for identifying and marking the line locations. The sequence is the whole lesson — locate, mark, then dig. A crew that starts digging in order to find out where the lines are has the sequence backwards, and the tool that makes the discovery is the one in a worker’s hands.
Who Gets the Call: Local Supervision or USA DIG
The call goes to the party that can actually find the lines: local area supervision — or the USA DIG organization, when appropriate — is called, and the request is made for identifying and marking the line location or locations. Note what the request is for. It is not a permission slip and not a formality; it asks the people with the records and the locating equipment to put the underground plant on the surface, as marks, before the excavation disturbs it. Until that identification happens, the digging does not start.
Two Working Days: The Notice That Makes Locating Possible
When USA DIG is called, its representatives need a minimum of two working days’ notice prior to the start of work. The notice period is not bureaucracy — locating is fieldwork. Records must be pulled, locators dispatched, and marks placed for every utility on the route, and none of that can happen between a morning phone call and an afternoon backhoe. Planning the call into the job schedule two working days ahead is what turns the locate from a hope into an appointment, and a job that cannot wait two days is a job that was scheduled without its locating step.
What the Caller Must Provide: The Information Checklist
The locate can only be as good as the information behind it, so N.4.4 lists what USA DIG needs from the caller:
- A minimum of two working days’ notice prior to the start of work — and the location, given precisely: name of county, name of city, name and number of street or highway marker, and nearest intersection
- The type of work
- The date and time the work is to begin
- The caller’s name, and the contractor or department name and address
- A telephone number for contact
- Any special instructions
Read the list as the locator’s working papers. The county, city, street, and nearest intersection pin the excavation to a findable spot — “out by the old plant” locates nothing. The type of work and the start date and time tell the locators what is being dug and when the marks must be down. The caller’s name, organization, address, and phone number give the locating organization someone real to call back when a line on the map does not match the ground. And special instructions carry the odd facts — gated access, a shifted dig area, a known private line — that never appear on any record drawing.
The Gap in the System: Utilities That Do Not Belong
USA DIG is a clearinghouse, not a census. Utilities that do not belong to USA DIG must be contacted separately, and the annex adds the reason in plain terms: USA DIG might not have a complete list of utility owners. A clear response from the one-call organization therefore does not prove the ground is empty — it proves the member utilities were located. The plant’s own private lines, a non-member utility’s feed, or an owner the clearinghouse does not list still have to be found by contacting their owners directly. Treating one call as total coverage is the underground version of assuming a wire is dead because it looks quiet.
Marked Before Work, and Kept in Front of the Crew
The procedure closes the loop on the surface: utilities that are discovered shall be marked before work begins. The marks are the excavation’s map, and like any map they only protect the people who keep reading them. Supervisors periodically refer the marked locations to all workers subject to exposure — including new employees, who arrive after the locating is done and may never have heard the original briefing. The new hand on the crew is exactly the worker most likely to dig in the wrong place, so the procedure builds the re-briefing in: marks on the ground, refreshed in the crew’s memory, for as long as the exposure lasts.
Worked Scenario
A contractor is hired to trench a conduit run across an industrial site to a new outbuilding, crossing ground that carries the plant’s power feed and at least two other utilities. The project manager builds the dig the N.4.4 way. Four working days before the scheduled start — ahead of the two-day minimum — she calls USA DIG with the full checklist ready: the county and city, the street name and number with the nearest intersection, the type of work (open trench for conduit), the start date and time, her name and the contractor’s name and address, her phone number, and a special instruction noting the locked gate on the east side. The member utilities mark their lines. But the plant’s own privately owned feed to an older building does not belong to the one-call system, so local area supervision is contacted separately and that line is located and marked too. On dig morning, the supervisor walks the marked locations with the whole crew — including a laborer who joined the job that day — and repeats the walk-down midweek when the trench line extends. The excavator opens ground that has already told the crew everything it knows, which is the only way underground work should ever start.
Common Mistakes and Safety Notes
- Digging to find out. Where a reasonable possibility of contacting lines exists, the call and the locate request come before excavation starts — not after the first strike.
- Calling the day before. USA DIG requires a minimum of two working days’ notice. A late call is a skipped locate wearing a scheduling excuse.
- Giving a vague location. The checklist wants the county, city, street name and number or highway marker, and nearest intersection. Imprecision in the call becomes imprecision in the marks.
- Assuming one call covers everything. Utilities that do not belong to USA DIG must be contacted separately — the organization might not have a complete list of utility owners.
- Letting the marks fade from memory. Discovered utilities are marked before work begins, and supervisors periodically refer their location to all exposed workers, including new employees.
- Forgetting the callback trail. The caller’s name, contractor or department name and address, and a contact telephone number are part of the request — the locators need a person, not just a place.
Summary
Section N.4.4 makes locating the first step of any excavation: before digging starts, wherever there is a reasonable possibility of contacting electrical or utility lines or equipment, local area supervision — or USA DIG, when appropriate — is called with a request to identify and mark the line locations. USA DIG needs a minimum of two working days’ notice and a complete information package from the caller: the notice plus the county, city, street or highway marker, and nearest intersection; the type of work; the date and time work begins; the caller’s name and contractor/department name and address; a contact telephone number; and any special instructions. The system has a known gap — utilities that do not belong to USA DIG must be contacted separately, because its list of utility owners might not be complete. Whatever is discovered is marked before work begins, and supervisors periodically refer the marked locations to every exposed worker, new employees included, so the map on the ground stays fresh in the crew’s mind.
Quick-Check Questions
1. When must the call for identifying and marking underground lines be made?
Answer: Before excavation starts, wherever there exists a reasonable possibility of contacting electrical or utility lines or equipment.
2. What is the minimum notice USA DIG requires before work begins?
Answer: A minimum of two working days’ notice prior to the start of work.
3. Name four of the items USA DIG needs from the caller.
Answer: Any four of: two working days’ notice with county, city, street name/number or highway marker, and nearest intersection; the type of work; the date and time work is to begin; the caller’s name and contractor/department name and address; a contact telephone number; and special instructions.
4. A USA DIG locate comes back clear for its members. Why might the ground still not be safe to dig blind?
Answer: Utilities that do not belong to USA DIG must be contacted separately — USA DIG might not have a complete list of utility owners, so a non-member line can still be present.
5. What must happen to discovered utilities, and how are their locations kept in front of the crew?
Answer: Utilities that are discovered shall be marked before work begins, and supervisors periodically refer their location to all workers subject to exposure, including new employees.
Based on NFPA 70E (2024), Informative Annex N, paraphrased for study.