What You’ll Learn
- What makes a lockout/tagout “simple” under G.4.0, and which sections of the sample program a simple job actually uses
- The ten steps of the G.5.0 lockout sequence, in order — from notification to the locked-out state
- How the absence-of-voltage test is bracketed: instrument inspection, prove on a known source, test, prove again (G.5.6–G.5.8)
- Where grounding fits in the sequence (G.5.9) and why it comes after the test
- The eight steps of G.6.0 that restore equipment to normal — including ground removal order, QC checks, and the rule that only the installer removes the device
First, Is It Simple? G.4.0 Draws the Line
A simple lockout/tagout is the sample program’s home ground: the procedure of G.5.0 applied to a job that does not trigger the complexity conditions — multiple energy sources, multiple crews, crafts, locations, or employers, unusual disconnecting means, particular switching sequences, or work extending to a new shift. Section G.4.0 defines the simple procedure by the sections it involves: G.1.0 through G.3.0 (purpose, responsibility, preparation), G.5.0 through G.9.0 (the sequence, restoration, multi-person and multi-shift rules, and the complex plan requirements they point to), and G.11.0 through G.13.0 (equipment, review, training). In practice, “simple” describes most single-source, single-crew jobs — one disconnect, one lock, one work session. The moment a second source or a second shift enters, the job stops being simple, and the written plan of execution and person-in-charge rules of the complex procedure take over. This article walks the two sequences every lockout shares: the ten steps of G.5.0 that take equipment out of service, and the eight steps of G.6.0 that put it back.
Step 1: Notify — and Know Your Sources (G.5.1)
Notification opens the sequence. The employees shall be notified that a lockout/tagout system is going to be implemented, and the reason for it — nobody in the area should learn about a lockout by finding their machine dead. The step also fixes what the qualified employee implementing the lockout must carry in their head before touching anything: the disconnecting means location for all sources of electrical energy, the location of all sources of stored energy, and knowledge of the hazards associated with electrical energy. Notification without that knowledge is just an announcement; the step pairs the two deliberately.
Steps 2–3: De-energize, Then See It Open (G.5.2–G.5.3)
To de-energize under G.5.2, if the electrical supply is energized, the qualified person disconnects the electric supply and relieves all stored energy — the capacitor charge and the spring tension from the Purpose section are handled here, at the disconnect, not discovered later at the work point. Step G.5.3 then verifies the physical break the preparation promised: wherever possible, the blades of disconnecting devices should be visually verified to be fully opened, or draw-out type circuit breakers verified to be completely withdrawn to the fully disconnected position. “Wherever possible” is an honest qualifier — enclosed devices may not show their blades — but where the state can be seen, the sequence requires eyes on it rather than trust in a handle position.
Steps 4–5: Apply the Devices, Then Try to Defeat Them (G.5.4–G.5.5)
Lockout/tagout devices are applied at G.5.4: all disconnecting means are locked (tagged) with lockout/tagout devices. The annex adds an informational note for the tagout-only case: examples of additional safety measures when tagout alone is used include opening, blocking, or removing an additional circuit element — because a tag by itself only warns, a tagout program strengthens it with a physical impediment. Then G.5.5 performs the sequence’s first self-check: attempt to operate the disconnecting means to determine that operation is prohibited. This is the try-start discipline applied to the disconnect itself — if the device can still be operated, the lockout has failed at step 5, in the open, instead of at step “someone restarts the machine during the work.”
Steps 6–8: Live-Dead-Live (G.5.6–G.5.8)
The absence-of-voltage test occupies three steps because it is really three acts. G.5.6: the test instrument is inspected for visible damage, and work does not proceed on an indication of damage until an undamaged device is available — a cracked meter is not a measuring tool, it is a rumor generator. G.5.7: proper instrument operation is verified on a known source of voltage, and then the test for absence of voltage is performed. G.5.8: proper instrument operation is verified on a known source of voltage again, after the test. The bracketing is the whole logic of live-dead-live: the first proof shows the instrument could have found voltage, the reading in the middle shows it found none, and the second proof shows the instrument did not die somewhere in between. Skip either proof and the zero reading is just a number a possibly broken tool displayed.
Step 9–10: Ground, and the Job Is Locked Out (G.5.9–G.5.10)
Grounding comes at G.5.9, after the absence of voltage is proven. Where required, a grounding equipment/conductor device is installed on the phase conductors or circuit parts, to eliminate induced voltage or stored energy, before touching them — the test proved the supply is off, but induced voltage from neighboring energized runs and residual stored charge are not the supply, and the ground is what keeps them bled off for the duration of the work. The step adds the fault-duty rule: where contact with other exposed energized conductors or circuit parts has been determined possible, ground connecting devices rated for the available fault duty are applied — a ground that cannot survive the fault it might have to carry is decoration, not protection. G.5.10 then closes the sequence with a statement of state: the equipment, the electrical source, or both are now locked out (tagged out). Ten steps, and the work itself can finally begin.
Eight Steps Back: Restoring to Normal (G.6.0)
Restoration under G.6.0 is a sequence, not an afterthought, and its order carries the safety logic. G.6.1: after the job or task is complete, visually verify that it is complete. G.6.2: remove all tools, equipment, and unused materials and perform appropriate housekeeping — nothing rides back into service inside the equipment. G.6.3: remove all grounding equipment, conductors, and devices — and note the order relative to what follows: grounds come off while the locks are still on, so the circuit is still secured while its protective short circuits are being lifted. G.6.4: notify all personnel involved that the lockout/tagout is complete, the electrical supply is being restored, and they are to remain clear. G.6.5: perform any quality control tests or checks on the repaired or replaced equipment or supply. G.6.6: remove the lockout/tagout devices — and the person who installed the devices is to remove them. G.6.7: notify the owner of the equipment or supply that it is ready to be returned to normal operation. G.6.8: return the disconnecting means to their normal condition. Eight steps, ending where the ten began: with the equipment back in its owner’s hands, deliberately.
Worked Scenario
An electrician is assigned to replace the starter on a single-source, 480 V conveyor drive motor — one disconnect, one crew, one shift: a textbook simple lockout. She walks G.5.0 in order. (1) She notifies the line operators that the drive is being locked out for a starter replacement, and confirms from the drawings that the single disconnect feeds the motor and that the only stored energy is the drive’s control capacitor. (2) She opens the disconnect and discharges the stored charge. (3) The disconnect is a visible-blade type, and she confirms the blades are fully open. (4) Her lock and signed, dated tag go on. (5) She tries the disconnect handle: it will not move — operation is prohibited. (6) Her meter shows no visible damage. (7) She proves it on a known 120 V source, then tests each phase at the starter: no voltage. (8) She proves the meter on the known source again. (9) The motor leads run in a tray beside an energized feeder, so she installs grounding devices rated for the available fault duty before touching the terminals. (10) The drive is locked out; the starter swap proceeds. Restoration walks G.6.0 back: work verified complete; tools and the old starter cleared out and the area cleaned; grounds removed while her lock is still on; the operators notified that power is being restored and to stand clear; a QC check of the new starter’s connections and settings; her lock and tag removed — by her, the installer; the equipment owner notified the drive is ready; and the disconnect returned to its normal, closed condition. Ten steps out, eight steps back, none improvised.
Common Mistakes and Safety Notes
- Calling a job simple because it looks small. Multiple sources, crews, crafts, locations, employers, unusual disconnects, particular switching sequences, or a second shift each make it complex — size is not the test.
- Skipping the try-start. G.5.5’s attempt to operate the disconnect is the lockout’s first proof; a lockout that was never challenged has never been tested.
- Testing with an unproven — or damaged — instrument. G.5.6 stops the sequence for a damaged meter, and G.5.7/G.5.8 bracket the absence-of-voltage reading with proofs on a known source, before and after.
- Grounding before testing. The sequence tests first (G.5.7) and grounds after (G.5.9); the ground then guards against induced voltage and stored energy for the whole job.
- Removing grounds after the locks. G.6.0 removes grounds at step 3, while locks are still on — locks come off at step 6, near the end.
- Letting someone else remove the device “to save time.” Under G.6.6, the person who installed the lockout/tagout devices removes them.
Summary
G.4.0 defines the simple lockout/tagout by the program sections it involves — G.1.0 through G.3.0, G.5.0 through G.9.0, and G.11.0 through G.13.0 — and jobs that cross into multiple sources, crews, or shifts leave the simple path for a documented complex plan. The G.5.0 sequence takes equipment out of service in ten steps: notify employees and know every energy and stored-energy source (G.5.1); de-energize, disconnect, and relieve stored energy (G.5.2); visually verify blades fully open or draw-out breakers fully withdrawn, wherever possible (G.5.3); lock (tag) all disconnecting means (G.5.4); attempt to operate the disconnect to prove operation is prohibited (G.5.5); inspect the test instrument for damage (G.5.6); prove it on a known source and test for absence of voltage (G.5.7); prove it on a known source again (G.5.8); install grounding devices where required, rated for the available fault duty where contact with other energized parts is possible (G.5.9); and arrive at the locked-out state (G.5.10). Restoration under G.6.0 returns in eight steps: verify the job complete, clear tools and materials and clean up, remove grounds, notify personnel to remain clear, run quality control checks, remove the devices — by the person who installed them — notify the owner, and return the disconnecting means to normal.
Quick-Check Questions
- How many steps are in the G.5.0 lockout sequence, and how many in the G.6.0 restoration?
Answer: Ten steps in the lockout sequence (G.5.1 through G.5.10) and eight steps in restoring to normal (G.6.1 through G.6.8). - What does G.5.5 require after the lockout/tagout devices are applied?
Answer: Attempt to operate the disconnecting means to determine that operation is prohibited. - What are the three instrument steps, G.5.6 through G.5.8, in order?
Answer: Inspect the instrument for visible damage and do not proceed if damaged; verify proper operation on a known source of voltage, then test for absence of voltage; verify proper operation on a known source of voltage again after testing. - Why does grounding (G.5.9) come after the absence-of-voltage test rather than before it?
Answer: The test first proves the supply is disconnected; the ground then eliminates induced voltage or stored energy before touching, and guards against them for the duration of the work. - Who removes the lockout/tagout devices under G.6.6?
Answer: The person who installed the devices.
Based on NFPA 70E (2024), Informative Annex G, paraphrased for study.